The building complex, consisting of seven floors above and below ground, was comprehensively refurbished between 2019 and 2021 and equipped with the highest safety standards and state-of-the-art building services.
After completion of the construction measure, the property was handed over to the current tenant and was sold to a new owner.
BCL was responsible for the construction logistics planning, for the updating of this and for the execution of construction logistics.
Consulting/planning
Execution
Location |
Ringbahnstraße Berlin Germany |
---|---|
Services | Planning & Execution |
Usage | Office building |
Start of construction | August 2019 |
Completion | December 2021 |
Project type | Construction (modernisation) |
Contracting entity | APOprojekt GmbH, branch Berlin |
Gross floor area (GFA) | 27000 m² |