In the first step, a total gutting was carried out, combined with extensive demolition measures and a complete dismantling of the existing façade, so that only parts of the shell remained. In the second step, the new building and revitalisation measures will be realised.
As the construction project is located in the inner city, embedded in the residential district of Frankfurt's Westend, it was necessary to keep the construction noise away from the residents. Thus, a 6-metre-high freestanding noise barrier was realised by BCL and erected towards the neighbouring property in order to reduce the noise pollution as far as possible.
BCL is responsible for the construction logistics planning and for the execution of construction logistics.
Special challenges: this is a complex inner-city construction project; the space conditions on and around the construction site are tight. In addition, noise protection measures were necessary.
Consulting/planning
Execution
Location |
Grüneburgweg 102 60323 Frankfurt/Main Germany |
---|---|
Services | Planning & Execution |
Usage | Hotel and residential tower with condominiums |
Start of construction | August 2017 |
Project type | Construction (modernisation) |
Building owner | RFR Holding, Hines und Revcap |
Contracting entity | HaP Frankfurt GmbH & Co. KG represented by HaP Komplementär GmbH, Ulmenstr. 18, 60325 Frankfurt/Main |
Architect | KSP Engel |
Gross floor area (GFA) | 40800 m² |