In the Hamburg district of Bahrenfeld, the ZRE - Zentrum für Ressourcen und Energie (Center for Resources and Energy) is currently under construction as a project of Hamburg Stadtreinigung (SRH). Nationally, this is one of the first facilities that, in addition to thermal utilization (waste incineration plant), also sorts residual waste.

The project

The construction and coordination of five sub-plants on a total area of approximately 31,200 m² also pose a complex challenge for construction logistics.

As part of our logistical services, we ensure access to the construction site, manage delivery traffic, and oversee storage areas to ensure a smooth construction process. Additionally, a disposal yard for construction waste separation and disposal is being set up, ensuring compliance with regulations, environmental protection, and contributing to minimizing construction costs.

Furthermore, we are responsible for operating and maintaining two 2000 kVA transformer stations to supply electricity to both existing consumers and the construction site.

Visualization of the front side of the Center for Resources and Energy (ZRE), Hamburg, Germany
© SRH
isualization of the front side of the Center for Resources and Energy (ZRE), Hamburg, Germany
© SRH

Services in detail

Consulting/planning

  • Construction logistics phase planning (updating)
  • Construction logistics manual (updating)

Execution

  • Construction site logistics coordination
  • Delivery traffic management (online notification)
  • Area management
  • W​aste disposal site setup/operation
  • ​​​​A​​​​ccess and entry control surveillance (video)/ patrolling
  • Construction site setup (construction fence, construction path lighting, etc.)
  • Transformer stations
  • Container facilities
  • Operations medic including medical container
  • Traffic management (warning barriers, traffic guidance planning)
  • Construction signage / emergency exit signage

Further information

Location Schnackenburgallee 100
22525 Hamburg, Germany
Germany
Services Planning & Execution
Usage Waste recycling center (operational site)
Start of construction June 2022
Project type Construction (new building)
Building owner Stadtreinigung Hamburg
Contracting entity Zentrum für Ressourcen und Energie, 20531 Hamburg
Architect Offices Gottlieb Paludan Architects, Copenhagen
Plot size 31200 m²

Sustainability

  • Bundling of delivery traffic flows
  • Separation of construction waste by type and disposal via certified companies