The construction and coordination of five sub-plants on a total area of approximately 31,200 m² also pose a complex challenge for construction logistics.
As part of our logistical services, we ensure access to the construction site, manage delivery traffic, and oversee storage areas to ensure a smooth construction process. Additionally, a disposal yard for construction waste separation and disposal is being set up, ensuring compliance with regulations, environmental protection, and contributing to minimizing construction costs.
Furthermore, we are responsible for operating and maintaining two 2000 kVA transformer stations to supply electricity to both existing consumers and the construction site.
Consulting/planning
Execution
Location |
Schnackenburgallee 100 22525 Hamburg, Germany Germany |
---|---|
Services | Planning & Execution |
Usage | Waste recycling center (operational site) |
Start of construction | June 2022 |
Project type | Construction (new building) |
Building owner | Stadtreinigung Hamburg |
Contracting entity | Zentrum für Ressourcen und Energie, 20531 Hamburg |
Architect | Offices Gottlieb Paludan Architects, Copenhagen |
Plot size | 31200 m² |