The quarter is divided into different construction areas and construction measures. Both living and working will be possible there. The Tempelhof-Schöneberg district office requested a comprehensive construction logistics plan for this building project in advance. In the form of a feasibility study, the risks were uncovered and proposed solutions were analysed and developed by BCL, taking into account all boundary conditions.
BCL was responsible for the construction logistics planning (service phases 1 to 3 according to AHO booklet 25).
Consulting/planning
Location |
Berlin, Germany Germany |
---|---|
Services | Planning |
Usage | Residential and commercial area |
Start of construction | January 2020 |
Completion | April 2023 |
Project type | Construction (new building) |
Contracting entity | DU Diederichs Projektmanagement AG & Co. KG, Haus Dorotheenstadt, Universitätsstraße 2-3 a, 10177 Berlin |
Architect | Various architects |