These venues are important cultural institutions in Cologne. Over the years, the buildings had become in need of renovation and were no longer up to date, which is why the renovation began in 2012.
The aim of the renovation was to address building physics, acoustic, and structural weaknesses in the existing structure, as well as to eliminate infrastructural and safety deficiencies, combined with optimizing operational and artistic processes.
However, construction activities were halted temporarily since 2015, except for minor measures and stage technology. Only after the revision of the planning, the works resumed in mid-2021, with BCL appointed and utilized as the construction logistics provider.
Consulting/planning
Execution
Location |
Offenbachplatz 50667 Cologne, Germany Germany |
---|---|
Services | Planning & Execution |
Usage | Cultural institution (opera, playhouse) |
Start of construction | January 2012 |
Project type | Construction (modernisation) |
Contracting entity | BÜHNEN KÖLN SANIERUNG, Offenbachplatz, 50667 Köln |
Architect | Architecture and artistic construction management: HPP Architects GmbH, architect: Remigiusz Otrzonsek |
Gross floor area (GFA) | 66184 m² |
Number of upper floors | 10 |
Number of basement floors | 3 |
Further information about the project can be found here: