Due to the growing population in the Ramersdorf-Perlach district and the structural condition of the old primary school and associated buildings, the city of Munich decided to gradually demolish the existing structures and replace them with a modern, needs-based new building.
In January 2021, construction work began with the children's centre, followed by the new sports hall and, with a slight delay, the new primary school, as well as the redesign of the outdoor spaces. The existing buildings remained in use until the completion of each new building, which posed a particular challenge for the construction logistics.
BCL was responsible for the construction logistics planning and execution.
Consulting/planning
Execution
Location |
Karl-Marx-Ring 63/71 81735 Munich Germany |
---|---|
Services | Planning & Execution |
Usage | School with sports hall, children's centre, municipal singing and music school |
Start of construction | April 2021 |
Completion | May 2024 |
Project type | Construction (new building) |
Contracting entity | City of Munich, Department of Education and Sports, Building Department (project management) |
Architect | Auer Weber Assoziierte GmbH, Haußmannstr. 103 a, 70188 Stuttgart |
Gross floor area (GFA) | 16076 m² |
Number of upper floors | 3 |
Number of basement floors | 1 |